Creating Template Tasks with Duration and Planned Hours Using Workfront Fusion
Introduction
Creating template tasks with duration and planned hours in
Workfront can be a bit tricky. This article will walk you through the
necessary steps to configure and successfully create template tasks with a
duration of 1 day and planned hours of 2 hours.
Steps
1.
Drop a “Create Record” module in the scenario
editor.
2.
Choose the correct Workfront connection and
select the Record Type as Template Task.
3.
Under the fields to map check the check boxes:
·
Duration Type
·
Duration Unit
·
Duration Locked
·
Work Locked
·
Name
·
Parent ID
·
Role ID
·
Template ID
·
Work (This field represents Planned Hours)
4. Perform Field Mapping
·
Map the fields as per your requirements.
·
Ensure that both Duration Locked and Work
Locked are set to Yes.
o
Note: This step is crucial. If these fields are
not locked, the duration and planned hours will not be properly set.
·
Another important point: Planned Hours is
represented by the field Work in the mapping section.
5.
After the running the scenario with this module,
the template task will be created as shown below.